Heating Plant Jug Novi Sad

INVESTOR: Logo centar doo

View All Projects

Works on the fabrication and assembly of the steel structure for the cogeneration plant included the reconstruction of the existing boiler house and the merging of these two structures into a unified whole.

The plant consists of two sections: the main building and an annex. The dimensions of the main building are 11.2 x 8.2m with a height of 14.67m, and the annex is 4 x 11.2m with a height of 7.5m, featuring platforms at levels 4.3m and 8.5m for equipment placement.

LOCATION: Novi Sad
TYPE OF STRUCTURE: Cogeneration plant – South Heating Plant
STRUCTURE DIMENSIONS: 11.7 × 11.1 × 14.67m
STRUCTURE WEIGHT: 56t + equipment installation
PROJECT DURATION: August 2019 – October 2019

Gallery

© 2024. Čelik doo. All rights reserved.