CHINA ENERGY ENGINEERING

China Energy Engineering Group Tianjin Electric Power Construction Co.

For the purposes of the project “Construction of a complex of facilities for the production of tires with accompanying infrastructure” in Zrenjanin, 5,000 tons of steel structures were produced.

The PCR passenger tire production facility is located within the LingLong International Europe factory complex and consists of four expansion steel production halls.

The halls are structurally multi-nave, with cantilevered reinforced concrete columns and a steel roof structure. The transverse spans of the hall are 19m, 24m and 25m.

For the needs of the project, steel supports for pipelines, platforms for silos, accompanying secondary structures, as well as crane track supports were also produced.

  • INVESTORChina Energy Engineering Group Tianjin
  • LOCATIONZrenjanin
  • OBJECT TYPEProduction plant,
  • DURATION 10.2020. – 06.2022.
  • CATEGORY

T. +381(0)21/847-290 office@celikdoo.rs

FOLLOW US

© 2023 Čelik LCC . All rights reserved.